Katse 1.1MW hydropower Generation Improvement

Image

The project aims to Construct 1.1MW mini hydro power generation plant at Katse.


Objective:
To supply, install and commission two (500kW) mini hydro turbines at Katse dam, including their control and interconnection to the national grid.
Activities of the Project
-Professional services (consultant) for design, procurement of contractor, construction supervision and close out contruction of Katse dam small hydropower improvement project Undertaking detailed engineering designs 
-Review of equipment specification, definition construction plan

Targets of the Project
-Preparation of the bidding documents - Jan 2023
-Contract signing- March 2023.
-Site survey, manufacturing, transportation - April 2023 to March 2024 
-Construction/erection and commissioning - April 2024 to December 2025.